Scala Santiago campus
Three hyperscale data centres in Chile by Scala Data Centers.
Scala Data Centers is building three hyperscale facilities in Chile at Curauma, Lampa and Huechuraba 2. The project includes a new power substation and uses certified renewable energy to serve cloud and AI demand in Latin America.
- Three hyperscale sites in Curauma, Lampa and Huechuraba
- USD 328 million financing package secured in 2025
- 100% certified renewable energy for operations
- 23 MW contracted IT capacity with 30 MW reserved
- Includes construction of Nova Lampa power substation
What it is
The Scala Santiago campus comprises three hyperscale data centre sites in Chile. Scala Data Centers operates the facilities at Curauma, Lampa and Huechuraba 2. The company describes itself as a leading platform for sustainable digital infrastructure in Latin America. These sites support the growing need for cloud computing and artificial intelligence services in the region. The project also involves the construction of the Nova Lampa substation to ensure reliable power delivery. Scala aims to position Chile as a key digital gateway between Latin America and the Asia-Pacific region.
How it came about
Scala Data Centers secured a USD 328 million international financing deal in July 2025. This funding supports the construction of the three data centres and the associated power substation. The transaction was backed by a consortium of global banks including MUFG, SMBC, BNP Paribas and Natixis. It represents the largest project finance deal for a single-country data centre initiative in Latin America. The deal was structured using Scala鈥檚 existing Chilean corporate entity rather than special purpose vehicles. This approach underwent due diligence under US and Chilean law. The project received the Digital Infrastructure Deal of the Year award for Latin America from IJGlobal.
The building and the halls
The campus consists of three distinct locations: Curauma, which is already operational, and the developing sites at Lampa and Huechuraba 2. The infrastructure is designed to meet hyperscale requirements. Construction of the Nova Lampa substation is a critical component of the build. The design targets best-in-class energy efficiency metrics. The company states that the facilities will comply with local environmental assessment requirements. These mandates include local hiring and community engagement programmes. The construction phase is expected to generate thousands of direct and indirect jobs in the regions where Scala operates.
Power and cooling
Power supply is a central focus of the project. The Nova Lampa substation is being built to ensure reliable delivery of electricity. Scala states that the new sites will operate with 100 per cent certified renewable energy. The design power usage effectiveness (PUE) is targeted to be below 1.45. The facility aims for zero-waste water operations. The initial phase has 23 megawatts of contracted IT capacity. An additional 30 megawatts are contractually reserved for future expansion under agreements with hyperscale customers. This structure provides financial scalability and strategic flexibility for growth.
What runs inside
The primary tenants for these facilities are hyperscale customers. The infrastructure supports the accelerating global demand for artificial intelligence and cloud services. By establishing this footprint, Scala intends to elevate Chile鈥檚 role as a strategic digital gateway. The connectivity aims to link Latin America with the Asia-Pacific region. The sites are built to handle high-density computing workloads typical of modern cloud providers. The pre-established agreements with significant clients ensure immediate utilisation of the reserved capacity.
The place
The three sites are located in Curauma, Lampa and Huechuraba in Chile. These locations were chosen to support regional expansion and sustainability goals. The project aligns with local regulatory requirements, including community engagement and hiring mandates. This contributes to economic development in the specific regions where the data centres are built. The strategic positioning helps connect Latin American markets with international networks. The presence of these facilities reinforces the country鈥檚 status as a hub for digital infrastructure.
Environment and impact
Scala emphasises its commitment to environmental, social and governance standards. The project uses green-labelled international debt aligned with the company鈥檚 Green Bond Framework. The facilities are designed for high energy efficiency and renewable power use. Local disputes or negative environmental impacts are not detailed in the provided text. Instead, the company highlights positive contributions such as job creation during construction. The project complies with local environmental regulations and engages with communities. This approach aims to balance rapid infrastructure growth with sustainable practices.
Network and links
The campus is positioned to serve as a digital gateway between Latin America and the Asia-Pacific region. While specific fibre routes or subsea cable landings are not listed, the strategic intent is to facilitate international connectivity. The hyperscale nature of the facilities implies robust network interconnection capabilities. The infrastructure supports the high-bandwidth needs of cloud and AI services. This connectivity is essential for linking regional users with global digital markets.
Questions people ask about Scala Santiago campus
Where are the Scala Santiago campus data centres located?
The campus includes three sites in Chile: Curauma, Lampa and Huechuraba 2. Curauma is already operational while the other two are under development alongside the Nova Lampa substation.
What type of energy powers these data centres?
Scala states that the new sites in Chile will operate with 100 per cent certified renewable energy. The project also includes a dedicated power substation to ensure reliable delivery of this green power.
How much power capacity does the project have?
The deal supports 23 megawatts of contracted IT capacity. An additional 30 megawatts are already contractually reserved for expansion under agreements with hyperscale customers.
Who financed the construction of the campus?
A consortium of four global banks provided the funding: MUFG, SMBC, BNP Paribas and Natixis. The total financing package reached USD 328 million, marking a major deal for Latin America.
Good reading and sources
There is no English Wikipedia article on Scala Santiago campus yet, so the facts on this page come from the sources listed above: finance.yahoo.com/news/scala-data-centers-closes-usd-140000016.html. Some are the subject's own pages, so its claims about itself are reported as its claims. EveryDatacenter wrote the text in its own words, with AI assistance, and compares it with the sources to make sure no passage is copied.