News
EveryDatacenter
Quality Technology Services

Quality Technology Services

American operator of carrier-neutral colocation data centres in the US and Netherlands

Quality Technology Services (QTS) is an American company that runs carrier-neutral data centres and sells colocation space. Chad Williams started it in 2003 by buying a Kansas facility, and it grew by buying and converting sites across the US and in the Netherlands before Blackstone bought it in 2021.

Share on WhatsApp

  • Founded in 2003 by Chad Williams with a single Kansas data centre
  • Runs 28 data centre locations across the United States and Netherlands
  • Richmond, Virginia campus converted from a Qimonda plant to 1.3 million sq ft
  • MAREA and BRUSA subsea cables land at the QTS Richmond Network Access Point
  • Blackstone bought the company for about $10 billion in August 2021

What it is

Quality Technology Services, usually shortened to QTS, is an American business that owns and runs carrier-neutral data centres and rents out colocation space, meaning customers place their own servers in shared halls. Its head office is in Overland Park, Kansas. The company works across North America and the Netherlands, with its busiest areas in Northern Virginia, Dallas/Fort Worth, Chicago, Hillsboro in Oregon and New Jersey, plus the United Kingdom and the Netherlands in Europe. In 2019 it reported revenue of $480 million and 612 staff. Blackstone bought the firm in 2021 for roughly $10 billion.

How it came about

Chad Williams set the company up in 2003 after buying a data centre in Kansas. It then expanded by buying other sites: a Suwanee, Georgia facility in 2005, a large Atlanta building and a New York area site in 2006, Silicon Valley space in 2007, and a Florida presence in 2008. In 2010 it took over a former Qimonda semiconductor site in Richmond, Virginia and turned it into a 1.3 million square foot mega data centre. The firm became public through an IPO in October 2013. Later moves included the Chicago Sun-Times plant in 2014, Carpathia Hosting in 2015, a New Jersey campus in 2016, Dutch sites in 2019, and a greenfield campus in Hillsboro, Oregon. Blackstone completed its purchase on 31 August 2021.

The building and the halls

QTS buildings range from converted industrial plants to purpose-built campuses. Its Richmond, Virginia site, once a Qimonda semiconductor plant, became a 1.3 million square foot mega data centre. In Atlanta the company bought a 960,000 square foot building in 2006 and later added land next to it for expansion, with more than 250,000 square feet of leasable capacity finished in 2020. Other holdings include a 92,000 square foot San Francisco site, a 260,000 square foot Irving, Texas building, and 40 acres in Irving bought for new construction.

Power and cooling

QTS is a member of RE100, a group of companies pledged to 100% renewable electricity. By 2021 it said eight of its facilities ran on renewable energy, and its Hillsboro, Oregon campus, developed from 2020 and completed in 2021, is described as running entirely on renewable power. The company was named the most sustainable business in the data centre industry by World Finance Magazine in 2019 and again in 2020. No figures for total power capacity are given here.

What runs inside

QTS sells colocation in carrier-neutral buildings, so customers can pick their own network providers. Its Richmond, Virginia site acts as a network access point: the MAREA and BRUSA subsea cable systems, run by Telxius, land there. That exchange point, known as the QTS Richmond Network Access Point, was co-founded by Clint Heiden, then QTS Chief Revenue Officer, and Vinay Nagpal of InterGlobix. In 2013 the company also took on the customers of First National Technology Solutions.

The place

The firm began in Kansas and keeps its headquarters in Overland Park. Its reach now spans fifteen US states, from Virginia and Georgia to Texas, Oregon and Arizona, plus two Dutch towns, Eemshaven and Groningen. A new site at Cambois in Northumberland, United Kingdom was announced in 2025, with the first phase due in 2026 and full completion planned for 2035. In April 2025 Chad Williams stepped down as Chief Executive Officer and Chairman to return to Quality Group of Companies, the family office from which QTS grew; David Robey and Tag Greason became Co-CEOs.

Environment and impact

In 2025 a QTS data centre in Fayetteville, Georgia used about 30 million gallons of water through connections that Fayette County had not been told about. QTS paid $150,000 in back fees after the matter came to light. Residents had complained of low pressure, and the county had already asked people to cut water use during a drought. The finding caused anger locally. On the environmental side, QTS reports partnerships with American Forests and World Vision from 2020 and its RE100 membership.

Network and links

The Richmond, Virginia campus is the company's main interconnection point. The MAREA and BRUSA subsea cables, operated by Telxius, terminate there, and the site is run as the QTS Richmond Network Access Point. QTS describes its buildings as carrier-neutral, meaning several network operators can serve customers inside them. The company also bought Globix Hosting LLC and NTT USA LLC in 2006, adding hosting and network reach in the New York City area.

Questions people ask about Quality Technology Services

What does QTS actually do?

It builds and runs carrier-neutral data centres and rents colocation space, letting customers house their own equipment in shared halls and choose their own network providers. It operates in the United States and the Netherlands, with a site planned in the United Kingdom.

Who owns QTS now?

Companies affiliated with the Blackstone Group completed their purchase on 31 August 2021 for about $10 billion. Blackstone Infrastructure Partners and BREIT agreed to pay $78 a share. Chad Williams stepped down as CEO and Chairman in April 2025.

Where are its biggest sites?

Its largest operating areas are Northern Virginia, Dallas/Fort Worth, Chicago, Hillsboro in Oregon and New Jersey, plus the United Kingdom and the Netherlands. In total it lists 28 locations across fifteen US states and two Dutch towns, Eemshaven and Groningen.

What happened with water use in Georgia?

In 2025 a QTS facility in Fayetteville, Georgia drew roughly 30 million gallons through connections not registered with Fayette County. QTS paid $150,000 in retroactive fees. Residents had complained of low water pressure during a drought and county restrictions.

How does QTS power its sites?

It belongs to RE100 and aims at 100% renewable electricity. By 2021 it reported eight facilities using renewable energy, and its Hillsboro, Oregon campus runs entirely on renewable power. World Finance Magazine named it the industry's most sustainable company in 2019 and 2020.

Good reading and sources

Where this page comes from

The facts on this page come from the Wikipedia article "Quality Technology Services", written by its contributors and used under the CC BY-SA 4.0 licence, and from its Wikidata record (CC0). EveryDatacenter rewrote the text in its own words, with AI assistance, and compares every page with the article to make sure no passage is copied. It may be reused under the same CC BY-SA 4.0 licence with a link back.

It may contain mistakes, and figures change over time. Nothing here is investment or buying advice. If something is wrong, tell us. Last refreshed 2026-11-14.

The weekly digest