Bitdeer
Crypto-mining and AI cloud operator with sites in the US, Norway and Bhutan
Bitdeer Technologies Group runs bitcoin-mining and AI cloud infrastructure from Singapore, with facilities in the United States, Norway and Bhutan. Spun out of Bitmain in January 2021 by Jihan Wu, it listed on Nasdaq in 2023 and has since shifted mining capacity toward AI and high-performance computing.
- Spun out of Bitmain in January 2021 by Jihan Wu
- Listed on Nasdaq in April 2023 at a $1.18 billion valuation
- Tydal, Norway site rated at 180 megawatts, moving to AI computing
- Knoxville site took 9.4 percent of its utility's electric sales in 2023
- Tether invested $100 million through a private placement in May 2024
What it is
Bitdeer Technologies Group is a Singapore-based company that mines cryptocurrency and rents out AI computing capacity. Founded in January 2021 as a spin-off from the chip maker Bitmain, it trades on Nasdaq under BTDR and employs 471 people as of 2025. Its sites sit in the United States, Norway and Bhutan, with an American head office in San Jose, California. The firm ranks among the biggest bitcoin miners by computing power. From 2023 onward it has pushed into AI cloud services, working with Nvidia and retooling mining halls so they can carry artificial-intelligence workloads instead of, or alongside, crypto.
How it came about
Bitdeer came into being in January 2021 when it separated from Bitmain, the bitcoin-mining chip business Jihan Wu helped start in 2013. Wu moved to Singapore and has chaired the new company since, also serving as chief executive. A merger with Blue Safari Group Acquisition Corp. was announced in November 2021; after delays, the Nasdaq listing arrived in April 2023 at a $1.18 billion valuation. A share buyback of up to $1 million followed that June. Tether put $100 million into the company through a private placement in May 2024. In April 2026 the firm unveiled its SEALMINER A4 mining chips, built to cut energy use at large scale.
The building and the halls
The portfolio mixes purpose-built mining halls with adapted industrial property. In Rockdale, Texas the operation occupies a former aluminium-smelting plant roughly an hour from Austin. A 31-acre plot in Massillon, Ohio was bought in 2023 for a new facility; two buildings there were damaged by fire in November 2025, and the fire service found no evidence of arson while leaving the cause open. Further plans announced in April 2026 cover a data centre in Niles, Ohio. Construction also began in July 2026 on a Sparks, Nevada factory for circuit boards, server chips and capacitor resistors, due to start work in January 2027.
Power and cooling
Electricity demand is substantial at individual sites. The East Knoxville, Tennessee plant drew 63 megawatts as of 2022 and was the largest industrial buyer from the Knoxville Utilities Board, taking 9.4 percent of that utility's electric sales in 2023. In Texas the Rockdale site joins ERCOT programmes that cut consumption when the grid is under strain. Norway's Tydal location is rated at 180 megawatts and is being switched from crypto mining to AI and high-performance computing. Bhutan work, begun with the government in 2023, backs a fund of up to $500 million for greener mining in the Himalayan kingdom.
What runs inside
Bitcoin mining remains the core activity, supported by the company's own SEALMINER chip line. Since 2023 an AI cloud arm has offered GPU capacity to business customers, drawing on halls first built for mining. The Nvidia partnership announced in November 2023 underpins that service, branded Bitdeer AI Cloud, with its first AI cloud data centre started in Singapore. In August 2026 part of the Tydal capacity was leased to Volta Infra Holdings for 16 years in a deal worth US$4.7 billion, supported by $1.3 billion of credit from J.P. Morgan.
The place
Sites sit where cheap industrial power and existing plant are available. Knoxville offered a large utility customer relationship; Rockdale provided a shuttered smelter near Austin; Ohio brought open land in Massillon and a planned project in Niles described as a $300 million investment with about 50 jobs. Tydal in Norway supplies a 180-megawatt footprint suited to heavy computing. Singapore serves as the group's base, chosen as the residence of founder Jihan Wu and later the site of its first AI cloud data centre.
Environment and impact
Local effects centre on electricity use and employment. In Knoxville the company accounted for 9.4 percent of the utility's electric sales in 2023 and had around 30 staff there in 2024. The Niles project is presented as bringing roughly 50 jobs. A fire at the Massillon construction site in November 2025 damaged two buildings; investigators recorded no signs of arson and did not settle on a cause. The Bhutan arrangement links mining growth with a fund aimed at greener operations.
Network and links
Grid ties matter more than carrier links in the published picture. The Rockdale facility takes part in ERCOT demand-response schemes, adjusting draw when the Texas grid is stressed. Norway's Tydal site feeds into a long lease with Volta Infra Holdings backed by J.P. Morgan credit. AI cloud customers reach GPU capacity through the Bitdeer AI Cloud platform built with Nvidia.
Questions people ask about Bitdeer
What does Bitdeer actually do?
It mines bitcoin at facilities in the United States, Norway and Bhutan, and it also rents GPU computing power for AI work. The company designs its own mining chips, sold under the SEALMINER name, and runs data centres it first built for crypto.
Where is the company based?
Headquarters are in Singapore, where founder Jihan Wu lives. The American head office is in San Jose, California. Operations stretch across Tennessee, Texas, Washington and Ohio in the United States, plus Tydal in Norway and a partnership in Bhutan.
How large is its power demand?
The Tydal site in Norway is rated at 180 megawatts. In East Knoxville, Tennessee the facility drew 63 megawatts as of 2022 and was the biggest industrial customer of the local utility board that year.
Who backs the company financially?
It trades publicly on Nasdaq under BTDR. Tether bought a $100 million stake in May 2024. A 16-year lease of Tydal capacity to Volta Infra Holdings in August 2026 was valued at US$4.7 billion and supported by $1.3 billion of credit from J.P. Morgan.
Is it only about crypto mining?
No. From 2023 the firm has built an AI cloud business with Nvidia, converting mining halls for artificial-intelligence and high-performance computing. The Tydal conversion began in March 2026, and a Singapore AI cloud data centre was started in late 2023.
Good reading and sources
- Official websiteOfficial site
- Across U.S., Chinese Bitcoin Mines Draw National Security Scrutiny (Published 2023)The New York Times, Article
The facts on this page come from the Wikipedia article "Bitdeer", written by its contributors and used under the CC BY-SA 4.0 licence, and from its Wikidata record (CC0). EveryDatacenter rewrote the text in its own words, with AI assistance, and compares every page with the article to make sure no passage is copied. It may be reused under the same CC BY-SA 4.0 licence with a link back.
It may contain mistakes, and figures change over time. Nothing here is investment or buying advice. If something is wrong, tell us. Last refreshed 2026-11-14.