Dublin

Europe's cloud base, where data centres use about a fifth of Ireland's electricity and new grid links are paused.

Dublin became Europe's main base for US cloud and internet companies after Google, Microsoft, Amazon and Meta set up their European headquarters in Ireland. Their data centres, and those of colocation firms, cluster in west Dublin at Clondalkin, Grange Castle, Blanchardstown and Profile Park. They now use more of the country's electricity than all urban homes.

Why Dublin

Ireland offered a low company tax rate, an English-speaking workforce, EU membership and a mild climate that allows free cooling much of the year. Microsoft opened a large data centre in Dublin in 2009, and Google, Amazon and others followed. Equinix, Digital Realty, Interxion and CyrusOne run colocation halls for the companies that work alongside them.

Grid limits

Data centres used about 21% of Ireland's metered electricity in 2023 and 22% in 2024, according to the Central Statistics Office. In 2022 the grid operator EirGrid said it would not connect new data centres in the Dublin area until about 2028, and the regulator set rules that new sites bring their own generation or storage.

Data centres of Dublin

Still to be written: Google data centers, CyrusOne.

Also tied to Dublin

Photo credits on this page

The small pictures above come from Wikimedia Commons under free licences. Some are cropped to fit.

The weekly digest

Every Monday: the data centre of the day, new pages on EveryDatacenter, and the conferences and anniversaries of the week ahead.