AI power cluster, United States
Memphis
Home of xAI's Colossus clusters, built in a former Electrolux factory and at sites across the Mississippi line.
Memphis became an AI hub in 2024 when Elon Musk's company xAI turned a former Electrolux factory in South Memphis into Colossus, a cluster of about 100,000 Nvidia H100 GPUs built in 122 days. A second, larger site, Colossus 2, followed in the Whitehaven area, with power plants across the state line in Southaven, Mississippi. The speed of the build, and its gas turbines, made it the most debated AI site in the US.
Building Colossus
The local grid could at first supply only a small part of what Colossus needed, so xAI brought in mobile gas turbines and Tesla Megapack batteries. The Tennessee Valley Authority and the city utility, MLGW, later upgraded the supply to about 150 MW. A cluster of about 110,000 Nvidia GB200-class chips came online at Colossus 2 around January 2026. xAI is also building a wastewater recycling plant to supply cooling water.
Air and the neighbourhood
South Memphis neighbourhoods such as Boxtown already lived beside several industrial plants. Residents and the Southern Environmental Law Center said xAI ran dozens of turbines without permits; xAI said they were temporary. The Shelby County Health Department issued a permit for 15 turbines in July 2025. Supporters point to investment and tax revenue; critics to air pollution in a mostly Black, lower-income area.